Washington Street Repaving Schedule

Winter Street Closed April 9th

Washington Street Repaving from Curve St. to Locust St.

Grinding of Washington Street is scheduled for the nights of April 23 & 24 
Additional road working will be conducted during the daytime on April 24 through the 26th 
Paving will begin at night around April 29 & 30 
Line Painting will be done at night on May 1 or 2 
All work is weather dependent but is planned to be done by the 300th Parade.