Winter Street Water Main Project Report 2

Winter Street Water Main construction is progressing ahead of schedule and budget. The Contractor, CJP & Sons of Millis has completed installation of the main line from Ashland Street to just beyond Little Road or about 85% of the new main line. The focus then shifted to replacing water services along the completed and tested water main.  All water services from Ashland Street to past Maple Street have been replaced. The crew will continue with replacing services in the direction of Little Road. The trenches for the sections where all the services have been replaced, will be paved flush with the existing roadway surface.