Library A/C and Roof Replacement
Progress Report Week of 7/16/2018
- Currently the roof portion of the library project is approximately 95% complete.
- Additional roof work will occur between July 16 and July 20.
- Stored materials, debris and equipment will be removed from the rear of the library on or about July 23.
- The project will become dormant for approximately five weeks when the replacement HVAC equipment will arrive on site.
- There are no more project update reports required until the HVAC equipment shows up on site.
Progress Report Week of 6/29/2018
- As of 6/27/18 the shingle roofing replacement is approximately 40% complete. Shingle installation completion is anticipated for 7/6/18.
- “Flat” roofing replacement is anticipated to occur between 7/9/18 and 7/12/18.
- There will be a lull in construction until September.